Campus Building Projects

Thanks to generous support from private donors, our student body and the State of Washington, the UW Bothell campus is experiencing unprecedented growth.  Read below to learn more about our ongoing projects.

 

 

Construction News 

**TRAFFIC ACTIVITY**

Expect periodic traffic routing around construction activities to complete sewer and water connections to existing utilities. Signage will be posted and flaggers will direct traffic for alternating lane closures.

 


Husky Hall

Week of June 17

  • June 17 and 18 - Traffic control on Campus Way NE from Husky Village/185th to Facilities Services/ 180th. UW IT is coordinating a fiber pull to support future telecomm services at Husky Hall. Expect periodic traffic routing around construction activities to complete sewer and water connections to existing utilities. Signage will be posted and flaggers will direct traffic for alternating lane closures.
  • During construction, no unauthorized personnel should be inside the fenced construction area or the building.

 


Sports Field

Week of June 17

The Sports and Recreation Complex opened on December 6, 2012. Learn more.

Watch the time-lapse video: How to Build a Sports Field in 60 seconds


  • The basketball court will be closed for maintenance the week of June 17th to 21st.

Please keep in mind that the regional trail is closed and the pedestrian/bicycle detour route is through campus on Campus Way NE. Please watch out for this additional “traffic” while driving on Campus Way NE.

 


UWB-3

Week of June 17

  • UW2 chilled water shutdown June 17-19. During this shutdown domestic water is available but cooling system water is not. Temperatures in UW2 may feel a bit warmer than usual depending on temperatures outside. Please lower blinds in the morning and afternoon to limit heat buildup. Facilities Services will monitor building temperatures.
  • Lower the chilled water line between UW2 and UW1. This water line is near the lower level east side of UW2. Heavy equipment will be in the area; be prepared to hear and feel the effects of construction if you are in this area.

 

Additional UWB3 information:

  • Walking paths to the north side of UW2 are CLOSED from upper parking lots, from library, and from 110th Ave NE. These paths will remain closed for the duration of the project.
  • Bike lockers on the southwest side of UW2 are RELOCATED to the south side of UW1 for the duration of the project. Other bike lockers are located south of LBA and north of the Library.
  • Smoking shelter on the north side of UW2 is CLOSED. Other smoking shelters are located on the south side of UW1 and the north end of the Promenade near the bus loop. This shelter will remain closed for the duration of the project.

 


Sarah Simonds Green Conservatory

Week of June 17

  • Classroom furniture move-in.
  • Department of Labor & Industries final inspection.
  • City of Bothell final inspections.
  • Greenhouse and Classroom punch list items. 

UPDATE: The Conservatory building structure completion is anticipated by the end of Spring Quarter 2013, but exterior landscape efforts will continue through the summer. As a result the regional trail detour will remain in place until the full scope of the project is complete.

The construction areas are fenced and campus construction will be ongoing through July 2014. Under no circumstances should any unauthorized personnel be inside any of the fenced construction areas. The construction areas are identified on the construction map at http://www.uwb.edu/getattachment/about/construction/uwb-constructionroute-campusmap-updateaugust-p2.pdf.

 


Veterans Archway

Week of June 17

  • Installation of sand and paver.

     

…The Veteran’s Archway will represent not only the sacrifices we continue to ask of our service people, but also the transition our veterans make from the military to academia, and the journey we all strive to make together…

 

Concept

Veterans have made unrivaled sacrifices for our community and our country, this archway is our way to show our appreciation for their service in a permanent monument. This reflective space will bring together our community both on and off the campus in a space created for reflection of veteran’s service to our country.

Goals

This archway is a place where veterans from around the area can reengage with the university and the community. The archway will be constructed to show our respect for their service and invite them to share their experiences. It is our hope that this space will create dialogue on local and global policy issues.

Cost

The Veterans Archway is anticipated to cost just under $60,000. This project will be 100% paid for by donations and no state or university money will be used. The archway is a gift to the university and our community by generous contributors and has been organized and planned by the UW Bothell Student Veteran’s Association.

If you would like to get involved with the development of the Veterans Archway or are interested in making a contribution please contact, Benjamin Wiselogle Veterans Archway Fund Chair or Derek Lane, President, Student Veterans Association.

 


 

Please contact Amy Van Dyke at avandyke@uwb.edu or 425-352-5261 if you have any questions about the projects.

Questions?

Contact Amy Van Dyke at 425-352-5261 or avandyke@uwb.edu